CVS Data Center Upgrades

Caliente Construction

About this Project

K CORP services included demolition of existing roof top air handlers, computer units inside the data center and related piping and ductwork. Installation of new rooftop air handlers, computer room units, ductwork, dampers, piping and controls were performed during off hours in order to minimize disruption to the existing operations of this facility. Temporary cooling was provided for the data center in order to maintain operations and redundancy as required. All existing work spaces were protected before each work activity to insure existing work spaces remained cleaned and undamaged. Each work activity included a work plan that was reviewed and agreed upon with facility personnel. Balance of new systems and commissioning was provided to verify proper performance and compliance with the specifications.